2017 PEI Highway Bundle
Alberton, Prince Edward Island
Federal contribution
$2.7M
$2,693,010
Federal share37%
of $7.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 28, 2017
2018
Built
Approved 8 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Government of Prince Edward Island
- Construction start
- May 15, 2017(actual)
- Construction end
- Jul 16, 2018(actual)
Against the original forecast
- Construction end7 weeks earlyforecast Aug 31, 2018