Pavement Rehabilitation Projects - Southern Alberta (2017)

Foothills No. 31, Alberta

completeHighways and RoadsNRP
Federal contribution
$17.4M
$17,350,500
Federal share50%

of $34.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
201820192020
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jul 15, 2017(actual)
Construction end
Jun 15, 2020(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Sep 1, 2017
  • Construction end9 months lateforecast Sep 30, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49169 in the federal list. How to read these figures.