Pavement Rehabilitation Projects - Southern Alberta (2018)
Federal contribution
$30.9M
$30,851,000
Federal share50%
of $61.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 20, 2017
201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Alberta Ministry of Transportation
- Construction start
- Mar 26, 2018(actual)
- Construction end
- Jul 30, 2020(actual)
Against the original forecast
- Construction start5 weeks earlyforecast May 1, 2018
- Construction end7 months earlyforecast Mar 1, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49172 in the federal list. How to read these figures.