Handi-Van Purchase
Federal contribution
$44,933
Federal share45%
of $100.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2018
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Argyle
- Construction start
- Aug 30, 2017(actual)
- Construction end
- Jan 11, 2018(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Jan 31, 2018
Also in Argyle
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49227 in the federal list. How to read these figures.