Deloraine-Winchester - Additional Compact Mobility Van

Deloraine-Winchester, Manitoba

completePublic TransitPTIF
Federal contribution
$21,950
Federal share50%

of $43.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Apr 18, 2017(actual)
Construction end
Jul 18, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Mar 20, 2017
  • Construction end5 months earlyforecast Dec 31, 2017

Also in Deloraine-Winchester

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49241 in the federal list. How to read these figures.