Gimli - Handi-Van Purchase
Federal contribution
$39,224
Federal share50%
of $78.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 29, 2017
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Gimli
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Nov 9, 2017(actual)
Also in Gimli
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49245 in the federal list. How to read these figures.