Powerview - Pine Falls - Handi-Van Purchase
Powerview-Pine Falls, Manitoba
Federal contribution
$22,580
Federal share50%
of $45.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Town of Powerview - Pine Falls
- Construction start
- Apr 6, 2017(actual)
- Construction end
- Aug 9, 2017(actual)
Against the original forecast
- Construction end5 months earlyforecast Dec 31, 2017
Also in Powerview-Pine Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49255 in the federal list. How to read these figures.