Rossburn Handivan Storage

Rossburn, Manitoba

completePublic TransitPTIF
Federal contribution
$42,363
Federal share41%

of $102.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Municipality of Rossburn
Construction start
Aug 1, 2017(actual)
Construction end
Mar 8, 2019(actual)

Against the original forecast

  • Construction end8 months lateforecast Jun 30, 2018