Rossburn Handivan Storage
Federal contribution
$42,363
Federal share41%
of $102.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Municipality of Rossburn
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Mar 8, 2019(actual)
Against the original forecast
- Construction end8 months lateforecast Jun 30, 2018
Also in Rossburn
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49258 in the federal list. How to read these figures.