Bridge Renewal

Bighorn No. 8, Alberta

completeHighways and RoadsNRP
Federal contribution
$16.7M
$16,691,425
Federal share50%

of $33.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2017
201820192020202120222023
Built

Approved 3 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
Province of Alberta
Construction start
May 15, 2017(actual)
Construction end
May 29, 2023(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jun 1, 2017
  • Construction end7 months lateforecast Oct 31, 2022