Construction of a cycling lane to support Highway 2 PULSE (Route 900) Bus Rapid Transit (BRT) Expansion between Galea Drive and Lake Ridge Road in Ajax
Federal contribution
$267,500
Federal share50%
of $535.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Durham
- Construction start
- Sep 18, 2017(actual)
- Construction end
- Dec 6, 2017(actual)
Against the original forecast
- Construction start9 months lateforecast Jan 1, 2017
- Construction end4 months earlyforecast Mar 31, 2018
Also in Durham
- Construction of Median Bus Rapid Transit Lanes on Highway 2, City of Pickering$45.8M
- Detailed Design and Construction of Bus Rapid Transit (BRT) Lanes in the Town of Ajax, Town of Whitby and City of Oshawa$23.5M
- Harmony Creek Water Pollution Control Plant Upgrades$7.8M
- Durham Region Transit Fleet Replacements - 24 conventional buses$5.9M
- Demolition and New Construction of Durham Region Transit Operations Building$5.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49368 in the federal list. How to read these figures.