On Board Bus Security Cameras

Durham, Ontario

completePublic TransitPTIF
Federal contribution
$789,953
Federal share30%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
201820192020
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Aug 4, 2017(actual)
Construction end
Jan 29, 2020(actual)

Against the original forecast

  • Construction start7 months lateforecast Jan 1, 2017
  • Construction end18 months earlyforecast Jul 31, 2021

Also in Durham

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49370 in the federal list. How to read these figures.