Back to projects

Durham Region Transit Mini- Bus Fleet Expansion - 2 mini-buses

Durham, Ontario

completePublic TransitPTIF
Federal contribution
$121,300
Federal share50%

of $242.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
2018
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Construction start
May 26, 2017(actual)
Construction end
Jun 29, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Jan 1, 2017
  • Construction end3 months lateforecast Mar 31, 2018

Also in Durham