Durham Region Transit Specialized Services Fleet Replacements - 8 specialized buses

Durham, Ontario

completePublic TransitPTIF
Federal contribution
$454,980
Federal share42%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
2018
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Mar 30, 2017(actual)
Construction end
Apr 30, 2018(actual)

Against the original forecast

  • Construction start3 months lateforecast Jan 1, 2017
  • Construction end4 weeks lateforecast Mar 31, 2018

Also in Durham

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49373 in the federal list. How to read these figures.