Improvements to the North Simcoe Commuter Lot through the installation of a paved surface and lighting.

Durham, Ontario

completePublic TransitPTIF
Federal contribution
$142,255
Federal share49%

of $293.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
2018
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Construction start
May 5, 2017(actual)
Construction end
Apr 19, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2017
  • Construction end3 weeks lateforecast Mar 31, 2018

Also in Durham

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49375 in the federal list. How to read these figures.