Preparation for Raleigh Garage Facility Expansion

Durham, Ontario

completePublic TransitPTIF
Federal contribution
$1.1M
$1,087,750
Federal share50%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 27, 2018
201820192020
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jun 26, 2017(actual)
Construction end
Sep 2, 2020(actual)

Against the original forecast

  • Construction start6 months lateforecast Jan 1, 2017
  • Construction end11 months earlyforecast Jul 31, 2021