Building expansion to accommodate future growth and life cycle renewal (Malton Satellite Terminal)
Federal contribution
$419,854
Federal share50%
of $839.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
201820192020
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Nov 15, 2017(actual)
- Construction end
- Nov 30, 2019(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 3, 2017
- Construction end20 months earlyforecast Jul 31, 2021