Lifecycle renewal/replacement of building systems (City Centre Transit Terminal)

Mississauga, Ontario

completePublic TransitPTIF
Federal contribution
$88,276
Federal share50%

of $177.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedJul 10, 2017
2018
Built

Approved 3 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Mississauga
Construction start
Dec 1, 2017(actual)
Construction end
Oct 31, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast Apr 3, 2017
  • Construction end5 months earlyforecast Mar 31, 2019