Lifecycle renewal/replacement of building systems (City Centre Transit Terminal)
Federal contribution
$88,276
Federal share50%
of $177.8K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
2018
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Dec 1, 2017(actual)
- Construction end
- Oct 31, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Apr 3, 2017
- Construction end5 months earlyforecast Mar 31, 2019