Lifecycle renewal/replacement of building systems to improve efficiency and to extend system useful life (Edward J. Dowling Transit Facility)
Federal contribution
$1.6M
$1,612,066
Federal share48%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
2018
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Dec 1, 2017(actual)
- Construction end
- Oct 31, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Apr 3, 2017
- Construction end2.7 years earlyforecast Jul 31, 2021
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49384 in the federal list. How to read these figures.