Lifecycle renewal/replacement of exterior door to extend the useful life (Edward J. Dowling Transit Facility)

Mississauga, Ontario

completePublic TransitPTIF
Federal contribution
$13,871
Federal share36%

of $38.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Mississauga
Construction start
Aug 1, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start7 months lateforecast Jan 1, 2017
  • Construction end3.3 years earlyforecast Jul 31, 2021

Also in Mississauga

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49385 in the federal list. How to read these figures.