Information Technology Project for The Vehicle Communication (VCOM) Radio Infrastructure for Transit iBus Communications
Federal contribution
$581,569
Federal share50%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
20182019
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Mar 29, 2019(actual)
Against the original forecast
- Construction end2.3 years earlyforecast Jul 31, 2021
Also in Mississauga