Installation of 100 additional MiWay Transit Shelters
Federal contribution
$1.3M
$1,255,546
Federal share50%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 31, 2017
2018
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Sep 1, 2017(actual)
- Construction end
- May 31, 2018(actual)
Against the original forecast
- Construction start6 months lateforecast Mar 1, 2017
- Construction end2 months lateforecast Mar 31, 2018
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49398 in the federal list. How to read these figures.