Back to projects

Acquisition of up to 3 new transit buses

Mississauga, Ontario

completePublic TransitPTIF
Federal contribution
$131,079
Federal share50%

of $262.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2017
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Mississauga
Construction start
Jan 1, 2017(actual)
Construction end
Oct 1, 2017(actual)

Also in Mississauga