Transit Bus Seat Modification on 84 buses
Federal contribution
$546,683
Federal share36%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
201820192020
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Dec 1, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction end19 months earlyforecast Jul 31, 2021
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49408 in the federal list. How to read these figures.