Etobicoke Creek Trail reconstruction - trail resurfacing, signage, trail markers and trail user-count technology

Mississauga, Ontario

completePublic TransitPTIF
Federal contribution
$850,822
Federal share37%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedJul 10, 2017
20182019
Built

Approved 3 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Mississauga
Construction start
Aug 3, 2017(actual)
Construction end
Jul 31, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 3, 2017
  • Construction end2 years earlyforecast Jul 31, 2021