Etobicoke Creek Trail reconstruction - trail resurfacing, signage, trail markers and trail user-count technology
Federal contribution
$850,822
Federal share37%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
20182019
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Aug 3, 2017(actual)
- Construction end
- Jul 31, 2019(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 3, 2017
- Construction end2 years earlyforecast Jul 31, 2021
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49421 in the federal list. How to read these figures.