Trail Reconstruction - Pheasant Run Park
Federal contribution
$96,677
Federal share50%
of $193.4K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
20182019
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Oct 2, 2018(actual)
- Construction end
- Jul 31, 2019(actual)
Against the original forecast
- Construction end4 months lateforecast Mar 31, 2019
Also in Mississauga
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49424 in the federal list. How to read these figures.