Trail Reconstruction - Stonewood Park
Federal contribution
$55,796
Federal share50%
of $111.6K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
20182019
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Jul 31, 2019(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 3, 2017
- Construction end4 months lateforecast Mar 31, 2019