Back to projects

Acquisition of new Intelligent Transportation System (ITS) equipment (i.e. Closed-Circuit Television, detection devices)

Mississauga, Ontario

completePublic TransitPTIF
Federal contribution
$38,016
Federal share48%

of $79.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
2018
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Mississauga
Construction start
Apr 1, 2017(actual)
Construction end
Dec 31, 2017(actual)

Against the original forecast

  • Construction end3.6 years earlyforecast Jul 31, 2021

Also in Mississauga