Replacement of traffic controllers/cabinets

Mississauga, Ontario

completePublic TransitPTIF
Federal contribution
$100,388
Federal share50%

of $201.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20182019
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Mississauga
Construction start
Apr 1, 2017(actual)
Construction end
Dec 17, 2018(actual)

Against the original forecast

  • Construction end12 months earlyforecast Dec 31, 2019