Pedestrian & Cyclist Access to Mississauga's Transitway & GO Transit Stations
Federal contribution
$3.4M
$3,436,655
Federal share46%
of $7.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
201820192020
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Mississauga
- Construction start
- May 1, 2017(actual)
- Construction end
- May 29, 2020(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Jun 1, 2017
- Construction end14 months earlyforecast Jul 31, 2021