Access A Bus Vehicle Purchases

Halifax, Nova Scotia

completePublic TransitPTIF
Federal contribution
$847,906
Federal share45%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 17, 2019
201720182019
Built

Approved 2.4 years before the announcement.

Program
Public Transit Infrastructure Fund
Construction start
Jan 1, 2017(actual)
Construction end
Nov 4, 2019(actual)

Against the original forecast

  • Construction end4 months lateforecast Jun 30, 2019

Also in Halifax

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49456 in the federal list. How to read these figures.