Back to projects

Duncan / North Cowichan Joint Utilities Board (JUB) Wastewater Outfall Relocation

Duncan, British Columbia

approvedWastewaterSCF
Federal contribution
$3.0M
$3,000,000
Federal share11%

of $27.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2017
today
201720192021202320252027
BuiltForecast
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
District of North Cowichan
Construction start
Mar 31, 2026(forecast)
Construction end
Mar 31, 2027(forecast)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49718 in the federal list. How to read these figures.