Back to projects

Full Service Transfer Station at the Mackenzie Regional Landfill

Fraser-Fort George, British Columbia

completeSolid Waste ManagementSCF
Federal contribution
$767,333
Federal share33%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2017
201820192020
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jun 25, 2019(actual)
Construction end
May 31, 2020(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 1, 2019
  • Construction end6 months lateforecast Nov 30, 2019

Also in Fraser-Fort George

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49720 in the federal list. How to read these figures.