Nanaimo Airport Expansion Project Phase 1 - Air Terminal Building

Nanaimo, British Columbia

completeRegional And Local AirportsSCF
Federal contribution
$2.5M
$2,487,489
Federal share33%

of $7.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2017
201820192020
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Nanaimo Airport Commission
Construction start
Jun 18, 2018(actual)
Construction end
Jan 30, 2020(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 30, 2018
  • Construction end4 weeks lateforecast Dec 31, 2019

Also in Nanaimo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49729 in the federal list. How to read these figures.