Back to projects

Pitt Polder Pump Station Replacement

Pitt Meadows, British Columbia

completeDisaster MitigationSCF
Federal contribution
$2.3M
$2,325,000
Federal share33%

of $7.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 11, 2017
2018201920202021
Built
Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Pitt Meadows
Construction start
Nov 21, 2018(actual)
Construction end
Mar 9, 2021(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Feb 12, 2021

Also in Pitt Meadows

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49734 in the federal list. How to read these figures.