Back to projects

Reconstruction of the grounds of the Recreation Center

Saint-André, Quebec

completeRecreationSCF
Federal contribution
$91,409
Federal share33%

of $274.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
201820192020
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Apr 1, 2019(actual)
Construction end
Feb 13, 2020(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Apr 29, 2019
  • Construction end3 months lateforecast Oct 31, 2019

Also in Saint-André

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49929 in the federal list. How to read these figures.