Irenée-Thibault Park Development
Saint-Damien-de-Buckland, Quebec
Federal contribution
$21,659
Federal share33%
of $65.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2017
20182019
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Parish Municipality of Saint-Damien-de-Buckland
- Construction start
- Nov 1, 2017(actual)
- Construction end
- Jan 10, 2019(actual)
Against the original forecast
- Construction start4 weeks lateforecast Oct 1, 2017
- Construction end2 months lateforecast Oct 31, 2018