Renovation of the recreation building

Saint-Elzéar (Chaudière-Appalaches), Quebec

completeRecreationSCF
Federal contribution
$365,465
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Sep 18, 2017(actual)
Construction end
Sep 24, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast May 8, 2017
  • Construction end9 months lateforecast Dec 15, 2017

Also in Saint-Elzéar (Chaudière-Appalaches)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49946 in the federal list. How to read these figures.