Construction of a community centre

Saint-Arsène, Quebec

completeRecreationSCF
Federal contribution
$814,177
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
20182019
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Sep 29, 2017(actual)
Construction end
Nov 19, 2019(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 31, 2017
  • Construction end23 months lateforecast Dec 31, 2017