Replacement of the arena refrigeration system and upgrading of the arena facilities

Sainte-Croix, Quebec

completeRecreationSCF
Federal contribution
$582,579
Federal share33%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
201720182019
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jun 29, 2016(actual)
Construction end
Oct 17, 2019(actual)

Against the original forecast

  • Construction start10 months earlyforecast May 5, 2017
  • Construction end2 years lateforecast Oct 16, 2017