Replacing the Refrigeration System and Upgrading the Ventilation System of the Arena
Federal contribution
$260,892
Federal share33%
of $782.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 20, 2017
20182019
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Sainte-Germaine-Boulé
- Construction start
- Sep 29, 2017(actual)
- Construction end
- Nov 19, 2019(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 3, 2017
- Construction end2.1 years lateforecast Sep 29, 2017
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49959 in the federal list. How to read these figures.