Construction of a sports complex
Federal contribution
$10.8M
$10,804,065
Federal share33%
of $32.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 20, 2017
20182019202020212022
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Regional County Municipality of Les-Pays-den-Haut
- Construction start
- Jul 1, 2018(actual)
- Construction end
- Sep 19, 2022(actual)
Against the original forecast
- Construction start23 months earlyforecast Jun 1, 2020
- Construction end3 months lateforecast Jun 30, 2022
Also in Sainte-Adèle
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49962 in the federal list. How to read these figures.