Design and Implementation Plan for Lake Louise - Banff Transit
Federal contribution
$35,000
Federal share50%
of $70.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 5, 2017
201720182019
Built
Approved 5 weeks before the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Bow Valley Regional Transit Services Commission
- Construction start
- Sep 1, 2016(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Dec 31, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49969 in the federal list. How to read these figures.