Renovation of the Roch Lasalle Arena

Crabtree, Quebec

completeRecreationSCF
Federal contribution
$63,789
Federal share33%

of $191.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 29, 2017
2018
Built

Approved 5 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of Crabtree
Construction start
May 30, 2017(actual)
Construction end
Feb 26, 2018(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Apr 10, 2017
  • Construction end6 months lateforecast Sep 8, 2017