Renovation of the Roch Lasalle Arena
Federal contribution
$63,789
Federal share33%
of $191.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 29, 2017
2018
Built
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Crabtree
- Construction start
- May 30, 2017(actual)
- Construction end
- Feb 26, 2018(actual)
Against the original forecast
- Construction start7 weeks lateforecast Apr 10, 2017
- Construction end6 months lateforecast Sep 8, 2017