Rehabilitation of the Sports Complex
Saint-Félix-de-Dalquier, Quebec
Federal contribution
$503,940
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 20, 2017
2018
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Saint-Félix-de-Dalquier
- Construction start
- May 17, 2017(actual)
- Construction end
- Aug 27, 2018(actual)
Against the original forecast
- Construction start3 months earlyforecast Aug 10, 2017
- Construction end3 months lateforecast May 31, 2018
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50088 in the federal list. How to read these figures.