Reconstruction of the Pointe-aux-Oies swimming pool facilities
Federal contribution
$84,333
Federal share33%
of $253.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2017
20182019202020212022
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Montmagny
- Construction start
- May 20, 2019(actual)
- Construction end
- Dec 16, 2021(actual)
Against the original forecast
- Construction start8 months lateforecast Sep 4, 2018
- Construction end2.7 years lateforecast Mar 31, 2019
Also in Montmagny