Conversion of a former presbytery into a community center
Saint-Félix-de-Kingsey, Quebec
Federal contribution
$147,043
Federal share33%
of $441.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 21, 2017
201820192020
Built
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Saint-Félix-de-Kingsey
- Construction start
- Apr 20, 2017(actual)
- Construction end
- Dec 19, 2019(actual)
Against the original forecast
- Construction start2 months earlyforecast Jul 3, 2017
- Construction end2.1 years lateforecast Nov 29, 2017
Also in Saint-Félix-de-Kingsey
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50133 in the federal list. How to read these figures.