Construction of a multifunctional community center
Federal contribution
$2.7M
$2,660,131
Federal share33%
of $8.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 1, 2017
201820192020
Built
Approved 7 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Cantley
- Construction start
- Dec 1, 2019(actual)
- Construction end
- Jul 3, 2020(actual)
Against the original forecast
- Construction start18 months lateforecast Jun 6, 2018
- Construction end14 months lateforecast May 1, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50140 in the federal list. How to read these figures.