Renovation of the Guylaine-Cloutier swimming pool

Montmagny, Quebec

completeRecreationSCF
Federal contribution
$273,321
Federal share33%

of $820.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
20172019202120232025
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Montmagny
Construction start
May 1, 2018(actual)
Construction end
Feb 17, 2025(actual)

Against the original forecast

  • Construction start12 months lateforecast May 8, 2017
  • Construction end7.5 years lateforecast Aug 18, 2017

Also in Montmagny

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50144 in the federal list. How to read these figures.