Renovation of the Guylaine-Cloutier swimming pool
Federal contribution
$273,321
Federal share33%
of $820.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 25, 2017
20172019202120232025
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Montmagny
- Construction start
- May 1, 2018(actual)
- Construction end
- Feb 17, 2025(actual)
Against the original forecast
- Construction start12 months lateforecast May 8, 2017
- Construction end7.5 years lateforecast Aug 18, 2017
Also in Montmagny
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50144 in the federal list. How to read these figures.