The Maison du Kamouraska

Kamouraska, Quebec

completeTourismSCF
Federal contribution
$776,540
Federal share33%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
May 11, 2017(actual)
Construction end
Oct 5, 2020(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Apr 1, 2017
  • Construction end3.2 years lateforecast Jul 30, 2017