Skating rink and skate park rehabilitation

Saint-Anaclet-de-Lessard, Quebec

completeRecreationSCF
Federal contribution
$43,254
Federal share33%

of $129.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Apr 15, 2017(actual)
Construction end
Feb 14, 2018(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Jun 1, 2017
  • Construction end3 months lateforecast Oct 31, 2017

Also in Saint-Anaclet-de-Lessard

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50149 in the federal list. How to read these figures.